The Arabian Gulf Oil Company (AGOCO) has begun operating well Z-13 in the Al-Bayda field and connecting it to the Al-Dur station after completing the mechanical connection work.
According to technical data, initial tests of the well showed a crude oil production rate of approximately 488 barrels per day with no associated water and a specific gravity of 32 API. The wellhead pressure was recorded at 130 PSI using a 20/64-inch choke valve, while the production separator pressure at the Al-Dur station ranged between 50 and 55 PSI.